When using EVM as the methodology for evaluating project performance, the first step would be to _ _ _ _ _ _ _ _ _
When using EVM as the methodology for evaluating project performance, the first step would be to :
Group of answer choices
Set a baseline plan.
Determine the project objectives.
Determine the project deliverables.
Analyze the project budget.
Review the project prioritymatrix