When working with a project team to obtain estimates of task durations, it is best not to ______________________. encourage overestimating encourage candor try to get
When working with a project team to obtain estimates of task durations, it is best not to ______________________.
encourage overestimating
encourage candor
try to get team members to provide honest expectations of task durations
ask team members to draw on their experience