When you have only $9,000 to support the above projects, which project (or projects) should be chosen under NPV method and explain WHY? use 10%
When you have only $9,000 to support the above projects, which project (or projects) should be chosen under NPV method and explain WHY?
use 10% discount rate
Consider the following three projects. Period T=0 T=1 T=2 T=3 Project A ($5,000) $1,000 $1,200 $1,200 $1,800 $1,800 $1,800 $1,800 Project B ($9,000) $1,500 $1,500 $2,500 $2,500 $2,500 $1,900 $1,900 Project C ($4,000) $900 $900 $200 $500 $500 $500 $500 T=4 T=5 T=6 T=7 Step by Step Solution