Which is the following best describes the bottleneck resource for a process? Its the resource that takes the longest time Its the resource with highest
Which is the following best describes the bottleneck resource for a process? Its the resource that takes the longest time Its the resource with highest utilization Its the resource that is fewest in number Its the resource with smallest capacity