Which lot-sizing technique orders the quantity needed during a predetermined time between orders? A. economic order quantity B. periodic order quantity C. lot-for-lot D. time
Which lot-sizing technique orders the quantity needed during a predetermined time between orders?
A. | economic order quantity | |
B. | periodic order quantity | |
C. | lot-for-lot | |
D. | time fencing | |
E. | part-period balanci |