Question

...
1 Approved Answer

Which of the following answers contains two of the most important pre-requsites for crashing a project schedule? A. Tasks being considered for crashing need to

Which of the following answers contains two of the most important pre-requsites for "crashing" a project schedule?

A.

Tasks being considered for "crashing" need to be on the critical path and the budget needs to have funds to support adding additional resource hours or overtime.

B.

Tasks being considered for "crashing" need to be on the critical path and the project needs to go through a formal change control process.

C.

The project needs to be at risk of scope creep and the project needs to go through a formal change control process.

D.

Tasks being considered for "crashing" cannot be on the critical path and the scope of the project needs to be at risk of being changed.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Ethics for Scientists and Engineers

Authors: Edmund G. Seebauer, Robert L. Barry

1st Edition

978-0195134889

Students also viewed these General Management questions