Which of the following does not accurately describe a fixed-price contract with Award Fee: 1) The Award Fee portion of a Fixed-Price contract with Award

Which of the following does not accurately describe a fixed-price contract with Award Fee:

1) The Award Fee portion of a Fixed-Price contract with Award Fee is paid in addition to the Fixed-Price if the contractor meets or exceeds the Award Fee Plan criteria.

2)Award-fee provisions may be used in fixed-price contracts when the government wishes to motivate a contractor and other incentives cannot be used because contractor performance cannot be measured objectively.

3) Fixed-Price Contracts with Award Fee include normal profit for satisfactory performance.

4) The award fee portion is earned only when the final cost is less than the price stated i the contract.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial economics

Authors: william f. samuelson stephen g. marks

7th edition

9781118214183, 1118041585, 1118214188, 978-1118041581

More Books

Students also viewed these Economics questions

Question

Write a Python program to check an input number is prime or not.

Answered: 1 week ago