Which of the following is a reason for the use of an activity-on-node (AON) diagram? To create a visual of the projects critical path. To
Which of the following is a reason for the use of an activity-on-node (AON) diagram?
To create a visual of the projects critical path.
To manage a project.
To sequence activities based on their dependency on other activities.
To examine expected activity duration times.
All of the above are reasons to use AON.