Question
1 Approved Answer
Which of the following is false? If an activity has a slack value greater than zero, it needs to be a critical activity If Activity
Which of the following is false?
If an activity has a slack value greater than zero, it needs to be a critical activity
If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity
Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time
Lateness in any of the activities located on the critical path would result in lateness in overall project completion time
If there is only one activity in a project, it needs to be a critical activity
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started