Question

1 Approved Answer

Which of the following is false? If an activity has a slack value greater than zero, it needs to be a critical activity If Activity

Which of the following is false?
If an activity has a slack value greater than zero, it needs to be a critical activity
If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B
Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time
Lateness in any of the activities located on the critical path would result in lateness in overall project completion time
If there is only one activity in a project, it needs to be a critical activity
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Awareness And Change

Authors: Frank Martin , John L. Thompson , Jonathan M.Scott

7th Edition

1408064022, 978-1408064023

More Books

Students also viewed these General Management questions