Which of the following is not a requirement of ABC Costing? Multiple Choice An ABC system must be strongly supported by top management in order
Which of the following is not a requirement of ABC Costing? Multiple Choice An ABC system must be strongly supported by top management in order to be successful. Activity costs must always be added to homogeneous cost pools. The design and implementation of an ABC system should always be assigned to a cross-functional team. Without the proper support, an ABC initiative will be abandoned by lower level employees