Which of the following is NOT one of the bottom - up approaches to estimating project time and cost? Group of answer choices Parametric procedures
Which of the following is NOT one of the bottomup approaches to estimating project time and cost?
Group of answer choices
Parametric procedures applied to specific tasks
Estimates for the WBS work packages
Learning curve
Template method
Range estimates