Which of the following is true concerning the work breakdown structure ( WBS ) ? Group of answer choices The PMI WBS and PRINCE 2
Which of the following is true concerning the work breakdown structure WBS
Group of answer choices
The PMI WBS and PRINCE product breakdown structure PBS are effectively the same thing.
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team.
The WBS is the bill of materials BoM needed to accomplish the work of the project.
The WBS is the same as the resource breakdown structure RBS