Which of the following projects should be accepted if there is no budget constraint? (Choose all that applies) Projects that have a positive NPV Projects
Which of the following projects should be accepted if there is no budget constraint? (Choose all that applies) Projects that have a positive NPV Projects that have an IRR > WACC Projects that have a PI (Profitability index) greater than 1