Which of the following statements is correct about the relationship between technical performance and Earned Value Management (EVM)? A. Technical Performance Measurement (TPM) analysis can
Which of the following statements is correct about the relationship between technical performance and Earned Value Management (EVM)?
A. Technical Performance Measurement (TPM) analysis can give early warning of issues that might impact cost and schedules performance.
B. Technical performance measures do not provide early warning of problems, whereas EVM data does
C. EVM performance data and technical performance do not deal with the same contract scope of work.
D. Technical performance should not be considered in conjunction with EVM analysis
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started