Question

1 Approved Answer

Which of the following will correctly calculate the free slack in an activity? 1 - Late finish of the activity - late start of the

Which of the following will correctly calculate the free slack in an activity?
1- Late finish of the activity - late start of the next activity
2- Late start of the activity -Earl start of the activity
3- late finish of the predecessor - early start of the successor
4- Minimum early start of all the successors - early finish of the activity
5- Either IS - ES or LF - EF

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions