Which of these is NOT a reason for listing assumptions in the cost estimate? a . Two people from different backgrounds may view a situation
Which of these is NOT a reason for listing assumptions in the cost estimate?
a Two people from different backgrounds may view a situation differently.
b Assumptions that are not true often cause more work or manifest as risks.
c As more details are available, a project manager may review assumptions to uncover those that have now proven to be false.
d Because assumptions reflect problems that will definitely happen during the course of the project.