Which of these statements is best? Select one: a. Slack is the time an activity can be delayed without impacting the completion time of the

Which of these statements is best?

Select one:

a. Slack is the time an activity can be delayed without impacting the completion time of the project.

b. In PERT, we assume that the project completion time can be modeled by the beta distribution.

c. In PERT, the variance in completion time is equal to the variance of the most time-consuming activity on the critical path.

d. The variance of the project completion time is equal to the sum of the variances of all the activities.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: M.E. Thukaram Rao

3rd Edition

8122433820, 978-8122433821

More Books

Students also viewed these Accounting questions

Question

Differentiate between intelligence testing and achievement testing.

Answered: 1 week ago

Question

List at least three advantages to using a consultant.

Answered: 1 week ago