Which of these statements is not true when you inactivate tasks ( avalable ony in Proped Professional ) in a project? Inactive tasks no longer
Which of these statements is not true when you inactivate tasks avalable ony in Proped Professional in a project?
Inactive tasks no longer affect the schedule
Project applies different formatting to inactive tasks
You can't edit the values of inactive tasks
Inactive tasks remain in the tasklist