Which one of the following is an example of a sunk cost? Group of answer choices A. $2,500 paid to assemble the new machinery B.
Which one of the following is an example of a sunk cost?
Group of answer choices
A. $2,500 paid to assemble the new machinery
B. $20,000 project that must be forfeited if another project is accepted
C. $4,500 reduction in current shoe sales if a store commences selling sandals
D. $1,500 of lost sales because an item was out of stock