Which results from the Define Activities process are used to sequence the project activities? (LO-6) Group of answer choices Activity attributes, activity list, and the
Which results from the Define Activities process are used to sequence the project activities? (LO-6) Group of answer choices Activity attributes, activity list, and the milestone list Milestone list, resource calendars, and the risk register Milestone list, resource calendars, and the scope baseline Activity list, milestone list, and the scope baseline