Which scheduling technique is commonly used in project management to determine the critical path? a ) Kanban b ) PERT ( Program Evaluation and Review
Which scheduling technique is commonly used in project management to determine the critical path?
a Kanban
b PERT Program Evaluation and Review Technique
c JIT JustinTime
d Flow production