Question

1 Approved Answer

Which statement is not consistent with capacity requirements planning, the process of determining short - term capacity requirements? Multiple Choice The production schedule established by

Which statement is not consistent with capacity requirements planning, the process of determining short-term capacity requirements?
Multiple Choice
The production schedule established by a MPS may or may not be feasible.
Planned-order releases from a MPS is one of the primary inputs to capacity requirements planning.
Load reports for each work centre are the key outputs from capacity requirements planning.
The MPS is never revised, it is considered frozen and therefore capacity must be planned accordingly.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Robert Libby, Patricia Libby, Daniel Short, George Kanaan, M

5th Canadian edition

9781259105692, 978-1259103285

Students also viewed these General Management questions

Question

What are the three steps used to analyze a significant interaction?

Answered: 1 week ago