Question
Whizmo Toy Company is interested in creating an MRP schedule for the manufacture of a new toy car. The Body Shop currently has a demand
Whizmo Toy Company is interested in creating an MRP schedule for the manufacture of a new toy car. The Body Shop currently has a demand for 2500 Toy Cars. It needs to set up this schedule for the toy car and all the components. The toy car is made up of one body assembly and 4 wheels. The body assembly is made up of one hood, 2 sides, and one trunk.There are other components for the body assembly but the company has plenty of those parts left over from a previous production. Hence, it is only concerned with the toy car, sub-assemblies and components identified above.The safety stock and allocated are satisfied from the total on hand.
Item | Toy Car | Body Assembly | Wheels | Hood | Sides | Trunk |
Total on hand | 300 | 500 | 1200 | 100 | 200 | 1,000 |
Safety stock | 100 | 50 | 400 | 0 | 100 | 0 |
Allocated | 0 | 50 | 200 | 0 | 0 | 0 |
Scheduled Receipts | -- | -- | -- | -- | -- | 1000 |
How many units of the sides, the wheels, and the trunk must be purchased to produce the demand of Toy Cars. Assume that all of the items On Hand include the Safety Stock and the Allocated. It is not necessary to provide the requirements by week.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started