Widget Co . needs to design a product layout for a new product, the amazing Thatsit. The company plans to use this new production line

Widget Co. needs to design a product layout for a new product, the amazing "Thatsit". The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day. The following table describes the tasks involved in the production of a "Thatsit".
TASK PREDECESSOR TIME(seconds)
U 4
V U 14
W V 12
X V 10
Y W 6
Z X, Y 8
For output to equal projected demand, what will be the last task performed at the second workstation of the production line which uses the minimum number of workstations? Hint: Use the heuristic rule "Assign the task with the most followers."
Balancing Formula
Multiple Choice
Y
U
X
V
W

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel, Jr., Margaret M. Sutton

6th edition

978-1119298854, 1119298857, 1119385628, 978-1119385622

More Books

Students also viewed these General Management questions