Winkeyand her mom, Twinkey, have identified nine (9) activities that are required to complete their next project and developed a resource loading table. Since they
Winkeyand her mom, Twinkey, have identified nine (9) activities that are required to complete their next project and developed a resource loading table. Since they each work eight (8) hours a day, they need your help to perform resource leveling on their project such that they can finish it by the close of business on Day 24. The total resource time in any day cannot exceed 16 hours. Complete the following:
1. What is the critical path? (1 mark) |
2. Which activities have float? (1 mark) |
3.Which days are over-loaded ( 2Marks ) |
4. Indicate how you would level the table in order to finish the project by day 24 ( 2 Marks) |
Predecessor | Duration | Resources | |
Z | none | 3 | 6 |
Y | none | 8 | 8 |
X | none | 4 | 8 |
W | Z | 6 | 5 |
V | Y | 2 | 6 |
T | X | 3 | 6 |
S | V | 8 | 8 |
R | T | 1 | 4 |
P | W, S, R | 6 | 6 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started