Within the initial level of the Capability Maturity Model (CMM) project teams: Select one: a. Work to strengthen their software development process b. Manage their
Within the initial level of the Capability Maturity Model (CMM) project teams: Select one: a. Work to strengthen their software development process b. Manage their efforts in an ad hoc fashion c. Define project goals clearly during a kick-off meeting d. Work to hand over their products to maintenance specialists
Step by Step Solution
There are 3 Steps involved in it
Step: 1