Work breakdown structure of some ATM software is given below in list form: TASK Duration Predecessor Requirement Analysis 1.1. Describe system architecture 20 days 1.2.

Work breakdown structure of some ATM software is given below in list form:

TASK Duration Predecessor

Requirement Analysis

1.1. Describe system architecture

20 days

1.2. Interview

12 days

1.3. Define and develop sw requirements

14 days

1.4. Define Interface Requirements

14 days

1.5. Prioritize and Integrate Requirements

11 days

1.3

1.6. System Security Analysis

22 days

1.2

1.7. Software Quality & Risk Analysis

14 days

1.5

1.8. Create Requirements Analysis Report

22 days

1.6 & 1.7

System Designing

2.1. Perform Architectural Designing

21 days

1.8

2.2. Design interfaces

21 days

1.4

2.3. Develop algorithms

12 days

2.1 & 2.2

2.4. Design test cases

12 days

2.3

2.5. Perform Detailed Design

8 days

2.1 & 2.2 & 2.3

2.6. Create Software Design specification

24 days

2.5

Implementation

3.1. Create Test Data

19 days

2.6

3.2. Create Source Code

19 days

2.6

3.3. Generate Object Code

30 days

3.2

3.4. Plan Integration

7 days

2.1, 2.2

3.5. Perform integration

9 days

3.3., 3.4

3.6. Document Object Model

10 days

3.5

Testing

4.1. Unit Testing

14 days

3.1, 3.2

4.2. Integration Testing

22 days

3.5

4.3. System Testing

13 days

4.2

4.4. Provide Feedback to Programmers

14 days

4.3

Operation & Maintenance

5.1. Final checks and verification

28 days

4.4

5.2. Perform Preventative Maintenance

1 day

5.1

5.3. Documentation & User Manual

17 days

1.8 & 2.6

5.4. Distribute software

5 days

5.1 & 5.2

5.5. Install Software

12 days

5.3& 5.4

5.6. Training

8 days

5.3 & 5.5

5.7. Perform Adaptive Maintenance

9 days

5.5

Using the above WBS,

-Create the Gantt chart for the project.

-How long will it take to complete this project? You may ignore inconsistencies in estimations.

-Name two of the critical tasks.

-Assuming that every person in the team is multi-functional, roughly how many people are required?

Please use Microsoft Excel

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Practical Database Programming With Visual Basic.NET

Authors: Ying Bai

1st Edition

0521712351, 978-0521712354

More Books

Students also viewed these Databases questions

Question

a cognitive reaction to the anticipation of future misfortune.

Answered: 1 week ago