work Problem 12 Question Help /Test Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: - Production plans for complete kits are as follows: Start assembling 17,000 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 10,500 kits in week 6 The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time=1 weekMinimum order quantity -5,500 Week - 1 2 3 4 Gross requirements 17.000 1.000 1.000 5 1.000 6 10,500 Start assembling 17,000 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 10,500 kits in week 6 - The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements All scheduled receipts, lead times, and beginning inventory levels are shown. BEE Click the icon to view the MRP records Construct the material requirements plan for item System unit (enter your responses as whole numbers) 4 1.000 5 1.000 6 10,500 System unit: Lead Time = 1 week: Minimum order quantity -5,500 Week 1 2 3 Gross requirements 17.000 1.000 Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts DOD DO DOD DOD DOD Enter your answer in the edit fields and then click Check Answer. More Info 4 1,000 5 1,000 6 10,500 System unit: Lead Time = 1 week; Minimum order quantity = 5,500 Week 23 - Gross requirements 17,000 1,000 Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts Planned orders 4 Speakers: Lead Time = 1 week; Minimum order quantity = 7,000 Week 1 2 3 Gross requirements Scheduled receipts 13,000 5 Print Done CHICU UUDIS Speakers: Lead Time = 1 week; Minimum order quantity = 7,000 Week 1 2 3 Gross requirements Scheduled receipts 13,000 Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders CD-ROM drivers: Lead Time = 1 week; Minimum order quantity = 18,000 Week 2 3 4 Gross requirements 5 6 iel More Info mer 13,000 Scheduled receipts Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders ner 5 CD-ROM drivers: Lead Time = 1 week; Minimum order quantity - 18,000 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 16,500 Net requirements Planned receipts Planned orders tfiel work Problem 12 Question Help /Test Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: - Production plans for complete kits are as follows: Start assembling 17,000 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 10,500 kits in week 6 The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time=1 weekMinimum order quantity -5,500 Week - 1 2 3 4 Gross requirements 17.000 1.000 1.000 5 1.000 6 10,500 Start assembling 17,000 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 10,500 kits in week 6 - The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements All scheduled receipts, lead times, and beginning inventory levels are shown. BEE Click the icon to view the MRP records Construct the material requirements plan for item System unit (enter your responses as whole numbers) 4 1.000 5 1.000 6 10,500 System unit: Lead Time = 1 week: Minimum order quantity -5,500 Week 1 2 3 Gross requirements 17.000 1.000 Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts DOD DO DOD DOD DOD Enter your answer in the edit fields and then click Check Answer. More Info 4 1,000 5 1,000 6 10,500 System unit: Lead Time = 1 week; Minimum order quantity = 5,500 Week 23 - Gross requirements 17,000 1,000 Scheduled receipts Projected ending inventory: 9,500 Net requirements Planned receipts Planned orders 4 Speakers: Lead Time = 1 week; Minimum order quantity = 7,000 Week 1 2 3 Gross requirements Scheduled receipts 13,000 5 Print Done CHICU UUDIS Speakers: Lead Time = 1 week; Minimum order quantity = 7,000 Week 1 2 3 Gross requirements Scheduled receipts 13,000 Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders CD-ROM drivers: Lead Time = 1 week; Minimum order quantity = 18,000 Week 2 3 4 Gross requirements 5 6 iel More Info mer 13,000 Scheduled receipts Projected ending inventory: 4,500 Net requirements Planned receipts Planned orders ner 5 CD-ROM drivers: Lead Time = 1 week; Minimum order quantity - 18,000 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 16,500 Net requirements Planned receipts Planned orders tfiel