Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Write down all the activities on the critical path. 2 5.2 Write down the shortest period in which the entire project can be completed under
Write down all the activities on the critical path. 2
5.2 Write down the shortest period in which the entire project can be completed under normal circumstances. 2
5.3 Calculate the total cost to complete the project in the time mentioned in 5.2 above. 3
5.4 Calculate the total cost to complete the project if it has to be completed in 28 weeks. 5 Total
Lungameni Ltd intends entering into a contract relating to a construction project to which the following data apply:
Preceding Duration (weeks) Variable cost (N$) Activity Activity Normal Crash Normal Crash
Fixed costs amount to N$500 per week
The project coordinator of Lungameni Ltd has developed a network diagram using the above information as follows:
A B C D E F G
-
-
- A A B, D C
15 19 9 6 14 9 8
12 14 5 5 9 6 3
4 500 4 000 2 500 1 700 4 300 2 600 1 800
5 100 4 500 4 500 1 940 5 050 3 440 3 400
AE
15/12
19/4
C 9/5
D 6/5
14/9
B
F 9/6
G
8/3
REQUIRED:
MARKS
5.1 Write down all the activities on the critical path. 2
5.2 Write down the shortest period in which the entire project can be 2
completed under normal circumstances.
5.3 Calculate the total cost to complete the project in the time mentioned in 3
5.2 above.
5.4 Calculate the total cost to complete the project if it has to be completed in 5
28 weeks.
Total
12
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started