Question
X Company currently buys a part from a supplier for $12.82 per unit but is considering making the part itself next year. This year, they
X Company currently buys a part from a supplier for $12.82 per unit but is considering making the part itself next year. This year, they purchased 3,000 units of this part. Estimated costs to make the part are:
Per-Unit | Total | ||
Direct materials | $3.34 | $10,020 | |
Direct labor | 3.47 | 10,410 | |
Variable overhead | 3.80 | 11,400 | |
Fixed overhead | 3.60 | 10,800 | |
Total | $14.21 | $42,630 |
Of the estimated fixed overhead, $3,888 are common costs that would be allocated to the part; the rest would be additional fixed overhead costs. X Company currently rents unused factory space to a tenant for $2,900; it will have to use this space to make the part.
2. If X Company will need 3,000 units again next year and continues to buy the part instead of making it, it will save????
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started