Question
XTi Co. gathered the following actual results for the current month: Actual Units produced 1,200 Direct materials purchased 6,400 lbs. @ $11 per pound for
XTi Co. gathered the following actual results for the current month:
Actual Units produced 1,200
Direct materials purchased 6,400 lbs. @ $11 per pound for $70,400; and used 5,800 lbs.
Direct labor cost (2,150 hours @$22 per hour) $47,300
Manufacturing overhead costs incurred: $19,350 Variable and $9,650 Fixed overhead.
The Static original budgeted production was 1,000 units. The Input standards were:
Std Quantity x Std Price per input =Std Cost per Output U
Direct materials 5 pounds/Output unit x $10/lb.
Direct labor 2 hrs./Output unit x $20/hr.
Variable manufacturing overhead 2 Direct labor hrs x $8 per hr = $16 per unit
Fixed mfg. overhead [Budget $10,000] 2 Direct labor hrs x $5 per hr = $10 per unit
1.What is the direct materials quantity variance? _____ A. $4400U B. 2000F C. 6400U D. 5800U E. None of these.
2.What is the direct labor quantity efficiency variance? _____ A. $5000F B. 700F C. 4300U D. 2000F E. None of these.
3.What is the fixed overhead production volume variance? _____ A. $200F B. 350F C. 200U D. 2000F E. None of these.
4. What is the variable overhead controllable variance? _____ A. 2,000F B. $150U C. 2150U D. 4300U E. None of these.
5. What is the direct materials price variance? ____ A. $2000F B. 5800U C. 4400U D. 6400 U E. None of these.
6. What is the total overhead variance? _____ A. $150U B. 2,000F C. 2200F D. 4300U E. None of these.
7. What is the direct labor rate price variance? _____ A. $4,800U B. 4,000U C. 4,300U D. 2,400U E. None of these
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started