Question

1 Approved Answer

Y Company estimated that its total overhead cost of R600 000. It is considering implementing activity-based costing. Three cost pools (and activity measures) have been

Y Company estimated that its total overhead cost of R600 000. It is considering implementing activity-based costing. Three cost pools (and activity measures) have been identified: machine-related (machine-hours), production orders (number of orders), and product testing (number of tests). The estimated overhead was assigned to the pools as follows: R200 000 to machine-related, R100 000 to production orders, and R300,000 to product testing. Y Company produces two products. The following information is available:

Product 1

Product 2

Machine-hours

40 000

10 000

Orders

800

200

Tests

6 000

9 000

Direct labour hours

25 000

15 000

The company currently uses traditional costing and allocates overhead based on direct labour hours.

Calculate how much of the overheads are assigned to Product 1 using ABC costing?

a.

R300 000

b.

R360 000

c.

R173 000

d.

R420 000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multi Level Finance And The Euro Crisis Causes And Effects

Authors: Ehtisham Ahmad, Massimo BordignonA, Giorgio Brosio

1st Edition

1784715107, 978-1784715106

More Books

Students also viewed these Finance questions