Year Project A Project B 0 R -10 000 R -10 000 1 6 500 3 500 2 3 000 3 500 3 3 000
Year Project A Project B
0 R -10 000 R -10 000
1 6 500 3 500
2 3 000 3 500
3 3 000 3 500
4 1 000 3 500
NB: Each project has a cost of R10 000, and the cost of capital for each is 12 percent
1. Calculate each project's payback period, net present value (NPV), internal rate of return (IRR), and profitability index (PI).
2. Which project or projects should be accepted if they are independent?
3. Which project should be accepted if they are mutually exclusive?
4. How might a change in the cost of capital produce a conflict between the NPV and IRR rankings of these two projects? Would this conflict exist if r were 5 percent? (Hint: Plot the NPV profiles.)
5. Why does the conflict exist?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started