Question
(YEARS OF NEW CONSTRUCTION WORKS) Yaman Construction Company has received the tender for the construction of a shopping center. Undertaken in 2018 the cost of
(YEARS OF NEW CONSTRUCTION WORKS) Yaman Construction Company has received the tender for the construction of a shopping center. Undertaken in 2018
the cost of this work is 900.000 TL and initially the cost is 750.000 TL. Information about the three-year construction is as follows.
2018 2019 2020
Annual Actual Cost 240,000 TL 435,000 TL 75,000 TL
Cumulative Cost Realized 240,000 TL 675.000 TL 750,000 TL
Remaining Estimated Completion Cost 360,000 TL 75,000 -
Issued Rights Invoices 120,000 TL 350,000 TL 430,000 TL
Amount collected 105.500 TL 347,000 TL 340,000 TL
Requested:
a) The rate at which the daily ledger (general) records to be made in 2019 are completed in relation to the construction in question
according to the method. Organize the relevant sections of the Profit or Loss Statement and the Balance Sheet.
b) Cost recovery of logbook (general) records to be made in 2019 in relation to the construction in question
according to the method. Organize the relevant sections of the Profit or Loss Statement and the Balance Sheet.
c) Make the journal ledger (general) records to be made in 2019 according to the completed commitment method. 2019
prepare the Profit or Loss Statement for the year and the Balance Sheets dated 31.12.2019.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started