You and your partner are assigned to the Juice Bar project for the next 6 months. Dr. K your sponsor has asked you how the

You and your partner are assigned to the Juice Bar project for the next 6 months. Dr. K your sponsor has asked you how the project is performing. Given the following cost data

Planned value =$12,000, Earned Value $10,000, Actual Cost $10,000, and Budget at completion $12,000. Determine the following: 1. How is the project doing ? Is it ahead or behind schedule?

2. Is it under or over budget 3. How much would it cost at the time of completion? Would it bewithin the stated budget.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management A Practical Introduction

Authors: Angelo Kinicki, Brian Williams

6th Edition

0078029546, 978-0078029547

More Books

Students also viewed these General Management questions