Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are a junior manager with expertise in project management and a member of a project team of a company that just won the bid

You are a junior manager with expertise in project management and a member of a project team of a company that just won the bid to develop a new internet banking management system for a major bank in South Africa. The project will entail the following activities along with their respective precedence, duration and cost.

Activity Code

Activity

Immediate Predecessor

Normal Time(Weeks)

Crashing Time(weeks)

Normal Cost

Crashing cost

1

A

12

9

$90000

$135000

2

B

A

14

12

100000

120000

3

C

10

9

40000

45000

4

D

C

17

14

220000

280000

5

E

C

18

16

224000

256000

6

F

C

12

10

16000

20000

7

G

B,D,E

15

13

264000

312000

8

H

F

8

8

82000

9

I

H

12

11

300000

330000

10

J

B

9

7

125000

175000

The project requires a crane that rents for $800 per week and a crew of general labour that cost $4500 per week. Ahead of the next project team meeting, the project manager has tasked you to develop the project schedule along with relevant analysis on possible cost savings related to completing the project ahead of schedule.

For the questions that follow, use the activity codes in place of the activity. For instance, activity B should be written as activity 2. That is, 2 stands for B. Thus, a critical path of say, CBJ must be written as 3210 in the space provided.

Note: All answers must be in numeric form, This is why activities are given number codes.

i. The latest start time for activity J in order to complete the project on time is Blank 1. Fill in the blank, read surrounding text. .

ii. The number of weeks for which activity B could be delayed without delaying the project is Blank 2. Fill in the blank, read surrounding text. weeks.

iii. The project completion time is Blank 3. Fill in the blank, read surrounding text. weeks.

iv. The critical path of the project (in terms of the activity codes, and in the right order) is Blank 4. Fill in the blank, read surrounding text. .

v. The total cost of the project within the normal time frame is $ Blank 5. Fill in the blank, read surrounding text. .

vi. The activity/activities to crash in order to take advantage of weekly indirect savings as far as it makes economic sense is activity/activities Blank 6. Fill in the blank, read surrounding text. . Please answer using the activity codes and in the order from minimum to maximum activity code.

vii. The total cost of the project if the action in question (vi) is carried out is $ Blank 7. Fill in the blank, read surrounding text. .

viii. If the project has to be completed in 40 weeks, then the activity/activities to crash when at week 41 in order to achieve the 40 weeks (using activity codes, and listing the smallest first) is Blank 8. Fill in the blank, read surrounding text. . Please answer using the activity codes and in the order from minimum to maximum activity code. For example, if the activities to crash to get to week 40 when on week 41 is C,I, provide the answer as Blank 9. Fill in the blank, read surrounding text. .

ix. The minimum total cost of the project if it has to be completed in 40 weeks through crashing is $ Blank 10. Fill in the blank, read surrounding text.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multicriteria Decision Making Systems Modeling Risk Assessment And Financial Analysis For Technical Projects

Authors: Timothy Havranek, Doug MacNair, James Wolf

3110765640, 978-3110765649

More Books

Students also viewed these Accounting questions

Question

List and describe four common types of database failure.

Answered: 1 week ago

Question

4. Devise an interview strategy from the interviewers point of view

Answered: 1 week ago