You are a manager at Northern Fibre, which is considering expanding its operations in synthetic fibre manufacturing. Your boss comes into your office, drops a consultant's report on your desk, and complains, "We owe these consultants $ 1.4$1.4 million for this report, and I am not sure their analysis makes sense. Before we spend the $ 18$18 million on new equipment needed for this project, look it over and give me your opinion." You open the report and find the following estimates (in millions of dollars): Sales revenue 25 000 25.000 25.000 25.000 - Cost of goods sold 15.000 15.000 15.000 15.000 = Gross profit 10.000 10 000 10.000 10.000 General, sales, and administrative expenses 1 440 1.440 1.440 1.440 Depreciation 1 800 1.800 1.800 1.800 - Net operating income 6.760 6.760 6.760 6.760 Income tax 2.366 2.366 2.366 2.366 Net income 394 1 394 4.394 4.394 All of the estimates in the report seem correct. You note that the consultants used straight-line depreciation for the new equipment that will be purchased today (year 0), which is what the accounting department recommended for financial reporting purposes. CRA allows a CCA rate of 45 %45% on the equipment for tax purposes. The report concludes that because the project will increase eamings by. $4.394$4.394 million per year for 10 years, the project is worth $ 43.94$43.94 million. You think back to your glory days in finance class and realize there is more work to be done! First you note that the consultants have not factored in the fact that the project will require $ 10$10 million in working capital up front (year 0), which will be fully recovered in year 10. Next you see they have attributed $ 1.44$1.44 million of selling, general and administrative expenses to the project, but you know that $ 0.7250 72 million of this amount is overhead that will be incurred even if the project is not accepted. Finally, you know that accounting eamings are not the right thing to focus on! a. Given the available information, what are the free cash flows in years 0 through 10 that should be used to evaluate the proposed project? b. If the cost of capital for this project is 15 % 15%, what is your estimate of the value of the new project