Question

1 Approved Answer

You are a project manager at Fabulous-Houses-R-Us (FHRU) located in London, Ontario.You are assigned as project manager on the following project for the Falcon family

You are a project manager at Fabulous-Houses-R-Us (FHRU) located in London, Ontario.You are assigned as project manager on the following project for the Falcon family (owner).FHRU is a general contractor that subcontracts work to professionals in the London area.You will have a site superintendent (employee of FHRU) available for the project for 50% of the time to provide direction to andoverview ofthesubcontractors.TheFalconfamilyalready ownsthelandonwhich thehouse willbe built.

Milestones:

  • StartofprojectAugust15
  • CityofLondonandotherpermitsapprovedbySeptember15
  • FoundationplacedbyOctober15
  • Houseindrycondition(roofon,wallsintact)November30
  • CityofLondonfinalinspectionbyFebruary15
  • Completion(move-inready)andtransfertoownerby February28

Based on below 16 risks, write Date Added ( Keeping in mind the start and completion date of the project), Status, Comments (confidence, level, evidence?) Also, Under qualitative, mention Probability rating, Impact rating and risk ranking of every Risk ID. In quantitative cost, mention Probability %, Impact $ and risk ranking of every Risk ID. Under quantitative time, mention Probability %, Impact (days) and risk ranking of every Risk ID.

Risk ID Category Cause Risk Effect Risk Description Initial Ranking Estimate Triggers Risk Owner Potential Responses
R11 Financial Cost estimation errors Inaccurate cost projections Budget overruns Inaccurate cost estimates can lead to financial strain and exceed the allocated budget. Medium Inadequate cost analysis Project Manager Mitigate - Conduct thorough cost analysis and seek input from experienced professionals.
R12 Technical Construction defects Poor workmanship or materials Reputational damage Defects in construction can result in poor quality and damage the reputation of FHRU. High Inspection identifies significant defects Site Superintendent Accept - Implement stringent quality control measures and address defects promptly.
R13 Commercial Changes in building regulations Updated or new construction codes Design modifications and delays Changes in regulations can require modifications to the architectural and engineering plans. Medium Introduction of new building codes Architect or Engineer Mitigate - Stay updated with local building regulations and consult with experts.
R14 Execution Subcontractor availability Shortage of skilled labor Delays in project milestones Difficulty in finding subcontractors may cause delays in completing the project. High Shortage of skilled tradespeople Site Superintendent Transfer - Develop relationships with a diverse pool of subcontractors and have backup options.
R15 Contractual/legal Insurance coverage gaps Insufficient insurance policies Liability and financial losses Inadequate insurance coverage can expose FHRU to significant financial risks in case of accidents or damages. High Inadequate insurance policy review Project Manager Transfer - Ensure comprehensive insurance coverage for all potential risks.
R16 Financial Financing difficulties Difficulty securing construction loans Cash flow problems Inability to secure financing may lead to delays or even project cancellation. High Lender rejecting loan application Falcon family Avoid - Secure pre-approved financing and diversify funding sources.
O1 Opportunity Favorable economic conditions Increased demand for new homes Increased profits Positive economic conditions can lead to higher demand and increased profitability for the project. Medium Economic growth and low interest rates FHRU Sales and Marketing Department Exploit - Increase marketing efforts and offer incentives to attract potential buyers.
O2 Opportunity Technology advancements Adoption of innovative construction methods Improved efficiency and cost savings Embracing new technologies can enhance construction processes and reduce project timelines. Low Introduction of breakthrough construction techniques Project Manager Enhance - Invest in research and development of innovative construction techniques.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions

Question

Write a Python program to check an input number is prime or not.

Answered: 1 week ago

Question

Write a program to check an input year is leap or not.

Answered: 1 week ago

Question

Write short notes on departmentation.

Answered: 1 week ago