You are a project manager for a construction project budgeted at $750,000. As of today, the project should be 45% completed but after reviewing the
You are a project manager for a construction project budgeted at $750,000. As of today, the project should be 45% completed but after reviewing the status of the scheduled tasks involved in the project it is evident that only 25% of the work has been completed. The team has spent $200,000 thus far.
Answer the following questions:
1. Describe the formula for each equation and provide the answer
- Determine Earned Value (EV)
- Determine Planned Value (PV)
- Determine Cost Performance Index (CPI)
- Determine Schedule Performance Index (SPI)
- Cost Variance (CV)
- Schedule Variance (SV)
2. What does this data tell you?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started