You are a project manager for a new product development project that has four levels in the work breakdown structure. The duration estimates have been
You are a project manager for a new product development project that has four levels in the work breakdown structure. The duration estimates have been compressed and a schedule created. What time management activity should you do NEXT?
Begin schedule control
Begin activity resource estimating
Analogously estimate the schedule
Gain approval for the schedule