Question
1 Approved Answer
You are a project manager working for a regional hospital company. You have been assigned the responsibility to manage a project that performs monthly security
You are a project manager working for a regional hospital company. You have been assigned the responsibility to manage a project that performs monthly security vulnerability assessments and addresses any identified vulnerabilities. You question the assignment because
A Security vulnerability assessments do not materially contribute to your organization's System for Value Delivery and should not be considered important enough to be classified as a project.
B
The recurring nature of the assessment in addition to the lack of a target end date means that this endeavor is not a project at all.
This endeavor cannot be considered a project because no start date is specified.
D A security vulnerability assessment produces no specific product, so it is not a project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started