You are a project manager. You have received a request from the stakeholders to provide more features to the product. Which tools and techniques do
You are a project manager. You have received a request from the stakeholders to provide more features to the product. Which tools and techniques do you use to process the request through "Perform Integrated Change Control" process?
a) Expert judgment and risk identification
b) Change control tools and project document updates
c) Expert judgment, meetings, and change control tools
d) Expert judgment, meetings, and stakeholder analysis