Question

1 Approved Answer

You are asked to produce the schedule and cost variance reports for the project progress meeting. What is the schedule variance ( SV ) and

image text in transcribed
You are asked to produce the schedule and cost variance reports for the project progress meeting. What is the schedule variance (SV) and cost variance (CV) if you are reporting for end period #17? Your team provided you following data for the end of period#17:
scheduled cost =$523,000
cumulative actual cost =$540,000
earned value =$535,000
SV=5,000;CV=-12,000
SV=-12,000;CV=5,000
SV=12,000;CV=-5,000
SV=5,000;CV=17,000
SV=-5,000;CV=12,000
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these Accounting questions