You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following

 

You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions: Project Plan: Duration: 200 Days BAC: $400k. At day 50: AC: $100K EV: $80k. What are CV and SV? What is going to be the EAC and Duration of the project if: A: We continue with the same rates. B: We fix the issues and return to the originally planned rates.

Step by Step Solution

3.44 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

Answer Question 1 i CV is the value of the work completed on the project so far This is calculated by taking the total budget for the project and subtracting the EV For this project the CV is 320000 i... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elementary Statistics A Step By Step Approach

Authors: Allan Bluman

8th Edition

73386103, 978-0073386102

More Books

Students also viewed these Finance questions