Question
You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following
You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions: Project Plan: Duration: 200 Days BAC: $400k. At day 50: AC: $100K EV: $80k. What are CV and SV? What is going to be the EAC and Duration of the project if: A: We continue with the same rates. B: We fix the issues and return to the originally planned rates.
Step by Step Solution
3.44 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Answer Question 1 i CV is the value of the work completed on the project so far This is calculated by taking the total budget for the project and subtracting the EV For this project the CV is 320000 i...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Elementary Statistics A Step By Step Approach
Authors: Allan Bluman
8th Edition
73386103, 978-0073386102
Students also viewed these Finance questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App