You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:

You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:

Project Plan: Duration: 200 Days BAC: $400k.

At day 50: AC: $100k EV: $80k.

What are CV and SV? What is going to be the EAC and Duration of the project if: A: We continue with the same rates. B: We fix the issues and return to the originally planned rates.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Project Management A Complete Introduction

Authors: Alison Dykstra

2nd Edition

0982703430, 978-0982703434

More Books

Students also viewed these General Management questions

Question

discuss the reliability of the data you have gathered;

Answered: 1 week ago

Question

undertake an initial analysis of your data;

Answered: 1 week ago