Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are at the end of Day 7 of a project. Your activities list, initial duration estimates, predecessors and actual finish times of activities are

You are at the end of Day 7 of a project. Your activities list, initial duration estimates, predecessors and actual finish times of activities are listed below. The project has a required completion time of 14 days, which has not changed since the start of the project. Create an updated network diagram for the project, incorporating the actual finish dates of the completed activities. Calculate an updated value of ES, EF, LS, LF, TS and FS for each activity. What is the most critical path(s) for the updated schedule? Activity ABCDEFGHIL J Initial Duration Estimate (days) 2342NH324 7 Immediate Predecessor A A B B C D. E H G, I Actual Finish Time Day 4 Day 5 Day 6 Day 7 I
image text in transcribed
You are at the end of Day 7 of a project. Your activities list, initial duration estimates, predecessors and actual finish times of activities are listed below. The project has a required completion time of 14 days, which has not changed since the start of the project. Create an updated network diagram for the project, incorporating the actual finish dates of the completed activities. Calculate an updated value of ES, EF, LS, LF, TS and FS for each activity. What is the most critical path(s) for the updated schedule

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MIS Essentials

Authors: David M Kroenke

1st Edition

0136075606, 9780136075608

More Books

Students also viewed these General Management questions

Question

Select one: Rachmaninoff Mussorgsky Chopin Paganini

Answered: 1 week ago