Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You are at the end of Day 7 of a project. Your activities list, initial duration estimates, predecessors and actual finish times of activities are
You are at the end of Day 7 of a project. Your activities list, initial duration estimates, predecessors and actual finish times of activities are listed below. The project has a required completion time of 14 days, which has not changed since the start of the project. Create an updated network diagram for the project, incorporating the actual finish dates of the completed activities. Calculate an updated value of ES, EF, LS, LF, TS and FS for each activity. What is the most critical path(s) for the updated schedule? Activity ABCDEFGHIL J Initial Duration Estimate (days) 2342NH324 7 Immediate Predecessor A A B B C D. E H G, I Actual Finish Time Day 4 Day 5 Day 6 Day 7 I
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started