You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project Year 0 - $48
You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project Year 0 - $48 - $99 Year 1 $25 $21 Year 2 $19 $38 Year 3 $21 $50 Year 4 $12 $61 s of the two projects? a. What are the IRR b. If your discount rate is 4.6%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the IRR s of the two projects? The IRR for project A is | %. (Round to one decimal place.)