You are coaching a junior project manager who is unsure of when to use contingency reserves. What will you tell her. a. Contingency reserves are
You are coaching a junior project manager who is unsure of when to use contingency reserves. What will you tell her. a. Contingency reserves are used for unanticipated occurrences b. Contingency reserves are used for anticipated but certain occureneces c. Contingency reserves are used for anticipated but uncertain occurrences d. Contingency reserves are used for unanticipated but certain occurencds