You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass,
You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path.
ID | Description | Predecessor | Time (days) |
A | Systems | None | 8 |
B | Subsystem A design | A | 2 |
C | Subsystem B design | A | 1 |
D | Subsystem C design | A | 2 |
E | Program A | B | 2 |
F | Program B | C | 10 |
G | Program C | D | 2 |
H | Subsystem A test | E | 5 |
I | Subsystem B test | F | 5 |
J | Subsystem C test | G | 5 |
K | Integration | H, I, J | 1 |
L | Integration test | K | 5 |
Calculate the free slack and total slack for all noncritical activities (Click to select)
How long will this project take?
How sensitive is the network schedule?
What is the total slack on D?
What is the total slack on E?
What is the Free slack on B?
What is the free slack on H?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started